Contract Data part one and Option X7
The September term start for the new classroom block appears only in the Scope. The completion date in Contract Data is later, and delay damages are £0 per day.
What a bidder does: Finishing late costs nothing, so the term date gets no priority over cheaper sequencing.
The fix: Make the term date a completion date or key date in Contract Data, with a delay damages rate based on the council's real cost, such as temporary classrooms.