CALONCALON

The terms, in plain English

Contract and procurement language used on this site. Across the site, these terms are underlined with a dotted line: hover over them or tap them for a short definition.

Activity schedule
The priced list of activities used under NEC4 Options A and C. Work that is in the Scope but missing from the activity schedule is not in the price.
Assessment summary
Under the Procurement Act 2023, the explanation each bidder receives of how its tender was scored against the award criteria.
Compensation event
An event listed in the NEC4 contract that, if it happens and is not the Contractor's fault, entitles the Contractor to more money, more time, or both.
Contract Data
The part of an NEC4 contract where the project details are filled in: dates, the options chosen, rates and named people. Part one is the Client's; part two is the Contractor's.
Delay damages
A fixed daily amount the Contractor pays if it finishes late. NEC4 secondary Option X7.
Early warning
An NEC4 notice either side gives as soon as it becomes aware of something that could increase cost, delay completion or affect performance.
ITT
Invitation to tender. The documents that tell bidders what to price, how to bid and how bids will be evaluated.
Main option
The NEC4 payment basis chosen for the contract, from Option A (priced contract with activity schedule) to Option F (management contract).
Order of precedence
A rule saying which document wins when two conflict. The NEC4 Engineering and Construction Contract deliberately has none; the Project Manager instructs how to resolve the conflict.
Physical conditions
NEC4 compensation event 60.1(12): physical conditions on site that an experienced contractor would have judged so unlikely that it would have been unreasonable to allow for them.
Prevention event
NEC4 compensation event 60.1(19): an event that stops the Contractor completing on time, which neither side could prevent and an experienced contractor would not reasonably have allowed for.
Quality weighting
The share of the evaluation score given to non-price questions, such as approach, people and programme.
Scope
The NEC4 document that says what the Contractor has to do and any constraints on how. Called Works Information in NEC3.
Secondary option
Optional NEC4 clauses the client chooses to include, such as X7 delay damages or X5 sectional completion.
Site Information
Information the client provides about the site and its surroundings, such as ground investigation reports. Bidders are entitled to price on the basis of it.
Z clause
A clause the client adds to change the standard NEC4 contract, under Option Z. Each one moves risk somewhere, and bidders price it.

Short explanations for general understanding, not legal advice. The contract wording always governs.

Get a quoteFree sample
Ask an NEC or JCT question