Pre-tender assurance for utilities and infrastructure owners, before a contractor is appointed.

Regulated programmes, tested before the market sees them

Water, energy networks and transport. Our practitioners have delivered regulated capital programmes from the contractor side, under NEC and JCT, and know where packages leak value.

Contract forms we review: NEC4, NEC3 and JCT

What we hear from teams like yours

Regulatory allowances

Under AMP8 (PR24) for water and RIIO-ED2 and RIIO-T3 for energy, every unpriced risk that becomes a compensation event comes out of a fixed regulatory allowance.

Outages, possessions and consents

Third-party dependencies are where Scope, Contract Data and Z clauses most often pull in different directions.

Programme-wide templates

Contract and scope templates used across a programme repeat the same gaps package after package.

The kind of issue we find

An illustrative example, from a fictional scheme.

Scope 6.2 and Contract Data

Scope 6.2 makes network outages 'subject to availability'. No outage windows are given in the Scope or the Contract Data.

What a bidder does: Waiting time cannot be priced, so bidders add a premium, qualify the bid, or argue every delay later.

The fix: Give outage windows in the Scope, so a missed window is a clear compensation event and the price reflects real working time.

What we check for utilities and infrastructure owners

  • Outages, possessions and third-party consents
  • Z clauses across programme-wide templates
  • AMP8 and RIIO allowances, and how risk is priced
  • Carbon requirements (PAS 2080) and how they are evaluated

Open the sample report

Protect public money. Deliver more efficiently.

See what a bidder would find in your next tender, before you spend anything.